Chevrolet Cruze manuals

Chevrolet Cruze Repair Manual: Installation Procedure

  1. Cut the front hinge pillar body in corresponding locations to fit the remaining original panel. The sectioning joint should be trimmed to allow a gap of one-and-one-half-times the metal thickness at the sectioning joint.
  2. Create a 50 mm (2 in) backing plate from the unused portion of the service part.
  3. Drill 8 mm (5/16 in) along the sectioning cut on the remaining original part. Locate these holes 13 mm (1/2 in) from the edge of part and spaced 40 mm (1½ in) apart
  4. Prepare all mating surfaces as necessary.
  5. Fit the backing plates halfway into the sectioning joints, clamp in place and plug weld to the vehicle.
  6. Align the front hinge pillar body.

  1. Drill 8 mm (5/16 in) for plug welding along the edges of the front hinge pillar body as noted from the original panel.
  2. Clean and prepare the attaching surfaces for welding.

  1. Position the front hinge 9. pillar body on the vehicle.
  2. Verify the fit of the front hinge pillar body.
  3. Clamp the front hinge pillar body into position.

  1. Plug weld accordingly.
  2. To create a solid weld with minimum heat distortion, make 25 mm (1 in) stitch welds along the seam with 25 mm (1 in) gaps between them. Then go back and complete the stitch weld.
  3. Apply the sealers and anti-corrosion materials to the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair.
  4. Paint the repaired area. Refer to Basecoat/Clearcoat Paint Systems.
  5. Install all related panels and components.
  6. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection.
  7. Enable the SIR system. Refer to SIR Disabling and Enabling.
Removal Procedure
Warning: Refer to Approved Equipment for Collision Repair Warning in the Preface section. Warning: Refer to Collision Sectioning Warning in the Preface section. Warning: Refer to Glass and She ...

Front Hinge Pillar Body Sectioning (MIG-Brazing)
Note: According to different corrosion warranties, only the regional mandatory joining methods are allowed ...

Other materials:

Installation Procedure
Align the rear side door outer panel. Verify the fit of the rear side door outer panel. Clamp the rear side door outer  panel into position. Pre-flanging the flange with BO-6396 pliers and BO-6392 tool kit . Continue to hammer in stages along the hem flanges. App ...

Traction Control System (TCS)
The vehicle has a Traction Control System (TCS) that limits wheel spin. On a front-wheel-drive vehicle, the system operates if it senses that one or both of the front wheels are spinning or beginning to lose traction. When this happens, the system brakes the spinning wheel(s), and/or reduces en ...

Power Steering Fluid Reservoir Replacement
Preliminary Procedure Remove as much power steering fluid from the remote power steering fluid reservoir as possible. Place drain pans under the vehicle as needed. Hose Clamp Procedure Compress the power steering fluid reservoir outlet and inlet hose clamp from the power ...

© 2011-2026 Copyright www.ccruze.com