  1. Cut the front hinge pillar body in corresponding locations to fit the remaining original panel. The sectioning joint should be trimmed to allow a gap of one-and-one-half-times the metal thickness at the sectioning joint.
  2. Create a 50 mm (2 in) backing plate from the unused portion of the service part.
  3. Drill 8 mm (5/16 in) along the sectioning cut on the remaining original part. Locate these holes 13 mm (1/2 in) from the edge of part and spaced 40 mm (1½ in) apart
  4. Prepare all mating surfaces as necessary.
  5. Fit the backing plates halfway into the sectioning joints, clamp in place and plug weld to the vehicle.
  6. Align the front hinge pillar body.

  1. Drill 8 mm (5/16 in) for plug welding along the edges of the front hinge pillar body as noted from the original panel.
  2. Clean and prepare the attaching surfaces for welding.

  1. Position the front hinge 9. pillar body on the vehicle.
  2. Verify the fit of the front hinge pillar body.
  3. Clamp the front hinge pillar body into position.

  1. Plug weld accordingly.
  2. To create a solid weld with minimum heat distortion, make 25 mm (1 in) stitch welds along the seam with 25 mm (1 in) gaps between them. Then go back and complete the stitch weld.
  3. Apply the sealers and anti-corrosion materials to the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair.
  4. Paint the repaired area. Refer to Basecoat/Clearcoat Paint Systems.
  5. Install all related panels and components.
  6. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection.
  7. Enable the SIR system. Refer to SIR Disabling and Enabling.
Removal Procedure
Warning: Refer to Approved Equipment for Collision Repair Warning in the Preface section. Warning: Refer to Collision Sectioning Warning in the Preface section. Warning: Refer to Glass and She ...

Front Hinge Pillar Body Sectioning (MIG-Brazing)
Note: According to different corrosion warranties, only the regional mandatory joining methods are allowed ...

Other materials:

Park Brake and P (Park) Mechanism Check
WARNING When you are doing this check, the vehicle could begin to move. You or others could be injured and property could be damaged. Make sure there is room in front of the vehicle in case it begins to roll. Be ready to apply the regular brake at once should the vehicle begin to move. Park on ...

Aluminum Wheel Refinishing
Finish Damage Evaluation Procedure Note: If the wheels are chrome-plated, do not re-plate or refinish the wheels. If the wheels are polished aluminum, do not refinish the wheels in the dealer environment. Utilize a refinisher that meets manufacturer guidelines. Inspect the wheel ...

Installation Procedure
Drill 8 mm (5/16 in) for plug welding along the edges of the front compartment upper side rail as noted  from the original panel. Clean and prepare the attaching surfaces for welding. Position the front compartment upper side rail on the vehicle. Verify the fit of the fr ...